North Anna ESP update

Yesterday I was fortunate enough to hear a presentation by Gene Grecheck of Dominion. He discussed progress on the North Anna early site permit (ESP) process. That’s a subject that dates back to some of the earliest days of this blog. Since the presentation ran for a full hour, I won’t try to repeat it here, but a couple of points seemed to be of particularly broad interest.

The first point was about how we in the industry continue to wait impatiently for a new plant order. On a personal note, I would like to observe that it’s funny how our perspectives change. Five years ago, we were thrilled when anyone would say "nuclear" in a context that was not pejorative. One year ago, we were thrilled to hear that Duke was going to pursue a construction and operating license. Now, we really want to hear about a contract to build a new plant. In a few years, even that won’t satisfy us, and we will want to hear about concrete pours.

But I digress. Gene did not discuss changes in perspective, but he did mention that some nuclear engineering professors had asked him why new plant orders were so slow in coming. Students of licensing will know the answer. The new licensing process (10 CFR 52) has numerous highly visible steps that can precede the actual order. In the old process (10 CFR 50), the early steps were not nearly so visible. (See slides 12-14 of this PowerPoint presentation on the NEI Web site for a visual comparison of the old and new processes.) Utilities, Gene explained, are taking the process one step at a time, as well they should.

The second point is that the step-by-step licensing process worked for Dominion. Those familiar with the North Anna ESP will know that cooling water has long been a bone of contention. Gene cleared up the history of that issue for me. Lake Anna was originally designed for four 800-MW (electric) units. After the Nuclear Regulatory Commission approved the construction permit, Congress passed the Clean Water Act, which gave the states the authority to regulate water use. The Virginia Department of Environmental Quality classifies evaporative cooling as consumptive water use, and it saw an additional reactor (with evaporative cooling) as imposing an excessive demand on the Pamunkey River. Dominion accordingly modified its ESP application so that a new reactor would use a wet/dry cooling system, even though adding a third reactor at North Anna would not impose a water demand that exceeds what the NRC had approved. The ESP process identified a problem (water supply) and required that it be solved at an early date. Although there was some schedule slippage, there was substantial benefit in that Dominion was able to solve the problem without costly backfits.

Comments

Rod Adams said…
It is generally cheaper to correct problems as early as possible. This explanation makes sense to me.

It also shows how the licensing process will differ from place to place, since some sites have either larger or smaller cooling water issues.

That is one reason why we have designed a plant that can operate effectively using air as the cooling medium. Some sites that can use a reliable power source have little to no water available.

As far as we know, there is not yet any regulation that prevents us from heating air and discharging that to the environment.

Rod Adams, Adams Atomic Engines, Inc.

Popular posts from this blog

An Ohio School Board Is Working to Save Nuclear Plants

Ohio faces a decision soon about its two nuclear reactors, Davis-Besse and Perry, and on Wednesday, neighbors of one of those plants issued a cry for help. The reactors’ problem is that the price of electricity they sell on the high-voltage grid is depressed, mostly because of a surplus of natural gas. And the reactors do not get any revenue for the other benefits they provide. Some of those benefits are regional – emissions-free electricity, reliability with months of fuel on-site, and diversity in case of problems or price spikes with gas or coal, state and federal payroll taxes, and national economic stimulus as the plants buy fuel, supplies and services. Some of the benefits are highly localized, including employment and property taxes. One locality is already feeling the pinch: Oak Harbor on Lake Erie, home to Davis-Besse. The town has a middle school in a building that is 106 years old, and an elementary school from the 1950s, and on May 2 was scheduled to have a referendu

Why Ex-Im Bank Board Nominations Will Turn the Page on a Dysfunctional Chapter in Washington

In our present era of political discord, could Washington agree to support an agency that creates thousands of American jobs by enabling U.S. companies of all sizes to compete in foreign markets? What if that agency generated nearly billions of dollars more in revenue than the cost of its operations and returned that money – $7 billion over the past two decades – to U.S. taxpayers? In fact, that agency, the Export-Import Bank of the United States (Ex-Im Bank), was reauthorized by a large majority of Congress in 2015. To be sure, the matter was not without controversy. A bipartisan House coalition resorted to a rarely-used parliamentary maneuver in order to force a vote. But when Congress voted, Ex-Im Bank won a supermajority in the House and a large majority in the Senate. For almost two years, however, Ex-Im Bank has been unable to function fully because a single Senate committee chairman prevented the confirmation of nominees to its Board of Directors. Without a quorum

NEI Praises Connecticut Action in Support of Nuclear Energy

Earlier this week, Connecticut Gov. Dannel P. Malloy signed SB-1501 into law, legislation that puts nuclear energy on an equal footing with other non-emitting sources of energy in the state’s electricity marketplace. “Gov. Malloy and the state legislature deserve praise for their decision to support Dominion’s Millstone Power Station and the 1,500 Connecticut residents who work there," said NEI President and CEO Maria Korsnick. "By opening the door to Millstone having equal access to auctions open to other non-emitting sources of electricity, the state will help preserve $1.5 billion in economic activity, grid resiliency and reliability, and clean air that all residents of the state can enjoy," Korsnick said. Millstone Power Station Korsnick continued, "Connecticut is the third state to re-balance its electricity marketplace, joining New York and Illinois, which took their own legislative paths to preserving nuclear power plants in 2016. Now attention should